Farhan Ahmed
Maintenance + Infrastructure Manager
Automation & Controls Support · Plant Systems
14+ years leading maintenance, reliability, and automation for a 200,000 sq ft, near-24/7 manufacturing facility—combining capital project delivery and hands-on PLC/SCADA troubleshooting with in-house plant operations software.
farhan.ahmed.tech110@gmail.comLinkedInExplore 8 Case Studies ↓
Background
I lead maintenance and automation for a 200,000 sq ft manufacturing plant that runs near-24/7, leading a five-member unionized maintenance team alongside departmental budget, PM programs, and procurement.
My background bridges hands-on work on the production lines themselves (mechanical, electrical and controls troubleshooting) with a foundation in IT and software development, which I have used to build several of the systems the plant runs on day to day.
Rather than relying only on off-the-shelf tools, I have built a live production monitor, a shift-end reporting system, a maintenance management system, a materials planning system, an RFI system and a shipping system in-house, each one solving a specific operational problem.
Certifications
Work history
Maintenance + Infrastructure Manager
2015 to present (2026) · Title on record: Maintenance Manager / Automation Support Specialist
- Led a five-member unionized maintenance team across scheduling, daily priorities, and plant reliability.
- Managed department budget and parts procurement, and work with vendors daily: arranging parts, bringing in third-party contractors for major repairs, and choosing the best window for PM.
- Troubleshot production-line equipment hands-on (mechanical, electrical, pneumatic, and PLC, HMI and SCADA faults) across multiple automated lines.
- Managed the 2024 server, operating system and control software upgrade for Floor Line 1 and Wall Line 1 as a project, with the manufacturer’s European team, in two weeks, keeping uptime at 80% or better on nine hour shifts.
- Ran the TigerStop Saw 1 project end to end (vendors, parts, 600V electrical drops, staging, commissioning support) and, with my team, maintained four TigerStop saw-positioning units for 10 years, helping reduce double handling and material waste.
- Designed and built the in-house systems shown below, used across maintenance, production and procurement.
IT Administrator
- Provided on-site IT support and systems administration for the facility.
- Administered ERP (Deacom) access and user accounts, and coordinated an ERP platform migration.
Junior Admin Support
- Sep 2012 to Oct 2013.
Systems & capital projects
Six in-house operational systems plus two major capital and automation projects—built to eliminate chronic losses, improve visibility, and protect uptime. Screens shown use sample data.
Materials Planning (MRP) and Cutlist System
We build custom homes, so no two jobs are the same. Each model has its own specifications and elevations, and customer changes keep architects and CAD designers revising whole units or sub-units. On a car line one model repeats and the materials are worked out once. Here they have to be worked out job by job, and kept current every time a design changes.
A data-driven materials planning system that connects AutoCAD cutlists to the production schedule. It places batch and multiple orders, reserves material for each job and manages inventory. Its optimizer works out the best stock lengths to buy, which keeps the waste factor as low as possible and cuts in-house cutting cost and material handling. Reminders follow job dates and orders. When a design changes, the revised cutlist is uploaded against the same phase and house or block number (including multi-story blocks) and overwrites the previous data. Repeat models and elevations reuse existing material data; jobs without a good match are flagged for review.
One current view of material needs across procurement, production and the shop floor, in a business where every home is different and designs keep changing. Less material waste, lower in-house cutting cost and less material handling, with the warehouse managed by job date. Used daily across three departments.
Recent jobs
| ID | Model | Phase / lot | Due | Source |
|---|---|---|---|---|
| #1042 | Model A1 | Ph 2 / BLK 4 | Oct 12 | Actual / Released |
| #1041 | Model A1 | Ph 2 / BLK 3 | Oct 9 | Actual / Released |
| #1039 | Model C3 | Ph 4 / BLK 1 | Oct 7 soon | Actual / Released |
| #1036 | Model B2 | Ph 3 / Lot 22 | Sep 24 overdue | Actual / Released |
| #1031 | Model D4 | Ph 1 / Lot 9 | Sep 18 overdue | Estimated / Model |
Stock by category
Fully reserved: order needed
| Part | Stock | Reserved | Free |
|---|---|---|---|
| EWP-B, 20 ft | 24 | 24 | 0 |
| JOIST-C, 14 ft | 60 | 60 | 0 |
6 jobs matched from EWP layout data. EWP jobs contain floor joist and beam material only, so wall lumber, plates and studs are not included. Upload the actual cutlist once the job is released.
Sample data. Selected screens only. The real system is much larger: batch and multi-job ordering, material reservation, the cutting optimizer screens, user management, settings, an activity log, inventory import, receiving, backflush and many more screens and features.
See all sample screens
Quick actions
Recent jobs
| ID | Model | Phase / lot | Due | Source | Status |
|---|---|---|---|---|---|
| #1042 | Model A1 | Ph 2 / BLK 4 | Oct 12 | Actual / Released | Active |
| #1041 | Model A1 | Ph 2 / BLK 3 | Oct 9 | Actual / Released | Active |
| #1039 | Model C3 | Ph 4 / BLK 1 | Oct 7 soon | Actual / Released | Active |
| #1036 | Model B2 | Ph 3 / Lot 22 | Sep 24 overdue | Actual / Released | Active |
| #1031 | Model D4 | Ph 1 / Lot 9 | Sep 18 overdue | Estimated / Model | Active |
Recent activity
- EWP layout job #1038 updatedSep 28, 7:02 AM
- Cutlist uploaded for job #1042Sep 27, 11:15 AM
- EWP layout job #1034 updatedSep 27, 8:40 AM
- Inventory import completedSep 26, 8:30 AM
- Job #1029 reservation releasedSep 25, 2:05 PM
Schedule view
| Lot / unit | Model | Wanted date | Matched job | Score | Materials | Data source | Actions |
|---|---|---|---|---|---|---|---|
| Lot 12 | A1 | Oct 5, 2026 | Own data uploaded | - | 132 items | Actual cutlist | ViewUpload cutlist |
| Lot 13 | A1 | Oct 8, 2026 | Matched to #1017 | 100% | 132 items | Estimated / Model | ViewUpload cutlist |
| Lot 14 | A1 | Oct 12, 2026 | Matched to #1017 | 90% | 128 items | Estimated / Model | ViewUpload cutlist |
| Lot / unit | Model | Wanted date | Matched job | Score | Materials | Data source | Actions |
|---|---|---|---|---|---|---|---|
| Lot 3 | C3 | Oct 20, 2026 | Matched to #1008 | 73% | 118 items | Estimated / Model | ViewUpload cutlist |
| Lot 4 | E5 | Oct 27, 2026 | No source found | - | - | - | Upload cutlist |
Job performance
Material and inventory
Procurement and shopping
Cutting and optimization
Production and backflush
System and administration
Stock by category
| Category | Parts | Stock | Reserved | Free |
|---|---|---|---|---|
| JOIST | 27 | 3,860 | 210 | 3,650 |
| EWP | 17 | 1,260 | 108 | 1,152 |
Fully reserved: order needed
| Part | Stock | Reserved | Free |
|---|---|---|---|
| EWP-B, 20 ft | 24 | 24 | 0 |
| JOIST-C, 14 ft | 60 | 60 | 0 |
Active reservations by job
| Job | Phase / lot | Lines | Qty | Due |
|---|---|---|---|---|
| J-1042 | Ph 2 / Lot 12 | 3 | 46 | Oct 12 |
| J-1041 | Ph 2 / Lot 11 | 3 | 46 | Oct 9 |
| J-1039 | Ph 4 / Lot 1 | 5 | 88 | Oct 7 |
| J-1036 | Ph 3 / Lot 22 | 2 | 60 | Sep 24 overdue |
| J-1034 | Ph 3 / Lot 20 | 2 | 34 | Oct 14 |
| J-1030 | Ph 3 / Lot 18 | 3 | 44 | Oct 16 |
Most reserved materials
- JOIST-C, 14 ft60 reserved
- JOIST-A, 16 ft58 reserved
- EWP-D, 24 ft40 reserved
- EWP-B, 20 ft24 reserved
Note: these are a few selected screens, shown with sample data. The real system is much larger. Not shown here: batch and multi-job ordering, material reservation, the cutting optimizer screens, user management, system and email settings, an activity log, inventory import, receiving, backflush and many more screens and features.
FL1 and WL1 control and SCADA platform upgrade (2024)
The servers, operating system and control/SCADA software behind two production lines (Floor Line 1 and Wall Line 1) had to be brought up to current versions, with production and safety as the priority.
Managed the upgrade as a project (scope, vendor coordination, schedule): server hardware and operating system, GE Proficy Machine Edition and the CIMPLICITY SCADA software to current versions. The manufacturer’s team (Randek) is in Europe, so I worked from 3:00 AM to 7:30 AM Eastern every day for two weeks to match their working hours and avoid overtime charges, with the option to switch back to the old system at any point and the production team kept informed throughout.
Finished in two weeks: uptime stayed at 80% or better on the nine-hour shifts, and the schedule avoided overtime charges from the manufacturer.
The upgrade window
A daily window that matched the manufacturer’s European team and protected production.
Two weeks, every day.
TigerStop automated saw units: 10 years of maintenance
Four TigerStop automated saw-positioning units in the facility, kept running by my team for ten years.
Ran the Saw 1 project end to end (vendors, parts, 600V electrical drops, staging) and took part in commissioning. Day to day: mechanical and electrical/electronic maintenance, plus support for the cut-optimization side of the units.
Accurate, optimized cutting helps reduce double handling and material waste.
How an optimizing saw works
About TigerStop. TigerStop builds automated positioning and push-feed systems for saws, from stops that attach to an existing saw to fully automatic optimizing saw stations. The optimization is there to cut scrap and wasted time.
Shift-end production reporting and labour cost
After each shift, production, downtime and labour cost were not available in a form the departments could act on together.
A reporting system for both automated and manual lines. Each line’s shift production, downtime and scrap are recorded and turned into a management dashboard, line-wise reports, a floor TV display with target gauges for each shift, and a weekly report comparing labour cost per unit against target.
Gives the team a clear outline for the next meeting with maintenance, procurement and production, so problems from one shift become actions for the next.
Production, last 5 working days
Production by line, this month
Top downtime reasons, this month
Recent submissions
Day shift
B shift
| Production line | Production | Cost / unit | Target / unit | Variance | Downtime |
|---|---|---|---|---|---|
| Auto Wall Exterior | 5,690 LF | $2.8787 | $2.45 | +0.4287 | 215 min |
| Auto Wall Interior | 3,210 LF | $1.1184 | $1.05 | +0.0684 | 90 min |
| Manual Walls | 6,880 LF | $1.3743 | $1.15 | +0.2243 | 110 min |
| Floor Line 1 | 20,370 SF | $1.3132 | $0.95 | +0.3632 | 520 min |
| Floor Line 2 | 5,090 SF | $2.0275 | $1.38 | +0.6475 | 200 min |
| Floor Line 3 | - SF | - | $1.75 | - | - |
Sample data. Layout mirrors the production system.
See all sample screens
Production, last 5 working days
Production by line, this month
Top downtime reasons, this month
Recent submissions
| Date | Line | Shift | Production | DT |
|---|---|---|---|---|
| Sep 29 | Exterior Wall | Day | 1,190 | 0m |
| Sep 29 | Manual Walls | Day | 1,070 | 25m |
| Sep 28 | Auto Floor 1 | B Shift | 3,980 | 65m |
| Sep 28 | Auto Floor 1 | Day | 2,950 | 20m |
| Sep 28 | Interior Wall | Day | 880 | 0m |
| Sep 25 | Auto Floor 2 | Day | 640 | 0m |
Production breakdown by line
| Day | Production | MH rate | Downtime | % target |
|---|---|---|---|---|
| Mon Sep 28 | 3,120 | 29.4 | 25 min | 63% |
| Tue Sep 29 | 4,210 | 31.8 | 10 min | 85% |
| Wed Sep 30 | no data | |||
| Thu Oct 1 | no data | |||
| Fri Oct 2 | no data | |||
| Week total | 7,330 | 35 min | ||
| Day | Production | MH rate | Downtime | % target |
|---|---|---|---|---|
| Mon Sep 28 | 4,310 | 34.1 | 40 min | 71% |
| Tue Sep 29 | 5,290 | 36.6 | 15 min | 87% |
| Wed Sep 30 | no data | |||
| Thu Oct 1 | no data | |||
| Fri Oct 2 | no data | |||
| Week total | 9,600 | 55 min | ||
Production and labour cost performance
| Production line | Production | Reg labour | OT | Total direct | Cost / unit | Target / unit | Variance | Downtime |
|---|---|---|---|---|---|---|---|---|
| WALL LINES | ||||||||
| Auto Wall Exterior | 5,690 LF | $15,820.00 | $560.00 | $16,380.00 | $2.8787 | $2.45 | +0.4287 | 215 min |
| Auto Wall Interior | 3,210 LF | $3,590.00 | - | $3,590.00 | $1.1184 | $1.05 | +0.0684 | 90 min |
| Manual Walls | 6,880 LF | $8,960.00 | $495.00 | $9,455.00 | $1.3743 | $1.15 | +0.2243 | 110 min |
| Wall subtotal | 15,780 | $28,370.00 | $1,055.00 | $29,425.00 | $1.8647 | 415 min | ||
| FLOOR LINES | ||||||||
| Floor Line 1 | 20,370 SF | $24,860.00 | $1,890.00 | $26,750.00 | $1.3132 | $0.95 | +0.3632 | 520 min |
| Floor Line 2 | 5,090 SF | $10,320.00 | - | $10,320.00 | $2.0275 | $1.38 | +0.6475 | 200 min |
| Floor Line 3 | - SF | $3,120.00 | - | $3,120.00 | - | $1.75 | - | - |
| Floor subtotal | 25,460 | $38,300.00 | $1,890.00 | $40,190.00 | $1.5786 | 720 min | ||
| GRAND TOTAL (labour and downtime) | $66,670.00 | $2,945.00 | $69,615.00 | 1135 min | ||||
Daily production breakdown
| Production line | Mon Sep 21 | Tue Sep 22 | Wed Sep 23 | Thu Sep 24 | Fri Sep 25 | Sat Sep 26 | Week total | Target | Variance |
|---|---|---|---|---|---|---|---|---|---|
| Auto Wall Exterior | 1,010 | 1,180 | 1,150 | 1,260 | 1,090 | - | 5,690 | 5,200 | +490 |
| Auto Wall Interior | - | 1,490 | - | 1,720 | - | - | 3,210 | 2,900 | +310 |
| Manual Walls | 1,980 | 1,790 | 1,340 | 1,250 | 520 | - | 6,880 | 6,400 | +480 |
| Floor Line 1 | 5,010 | 4,690 | 3,720 | 5,130 | 1,820 | - | 20,370 | 18,000 | +2,370 |
| Floor Line 2 | 1,180 | 930 | 1,010 | 950 | 1,020 | - | 5,090 | 4,400 | +690 |
| Floor Line 3 | - | - | - | - | - | - | - | 3,600 | -3,600 |
Live production dashboard: hourly output vs target
The production team needed to see during the shift, not after it, whether they were on pace to meet the target. A commercial web visualization license for the SCADA system was also expensive.
A real-time web monitor for the floor screens. Production points logged from the SCADA system into SQL drive an hourly production log for each jig: target per hour, square feet manufactured, panels produced, target achieved and output variance against target, plus the bridge idle time for the shift.
The production team sees the shift hour by hour and can react before the target is missed, without buying the vendor’s web license.
Hourly production log
| Time | Jig | Target / hr | SQF | Panels | Target achieved | % | Missed |
|---|---|---|---|---|---|---|---|
| 6:30-7:30 | Jig 1 | 400 | 352 | 2 | 88% | −48 | |
| 7:30-8:30 | Jig 3 | 400 | 418 | 2 | 104% | +18 | |
| 8:30-9:30 | Jig 1 | 400 | 296 | 1 | 74% | −104 | |
| 9:30-10:30 | Jig 3 | 300 | 262 | 1 | 87% | −38 | |
| Total | 1,500 | 1,328 | 6 | 89% | −172 |
Sample data. Layout mirrors the production screen.
See all sample screens
| TIME | JIG | SQF PER HOUR TARGET | SQF MANUFACTURED | PANELS PRODUCED | TARGET ACHIEVED | SQF OPPORTUNITY MISSED |
|---|---|---|---|---|---|---|
| 6:30-7:30 | Jig 1 | 400 | 352 | 2 | 88% | -48 |
| 7:30-8:30 | Jig 3 | 400 | 418 | 2 | 104% | +18 |
| 8:30-9:30 | Jig 1 | 400 | 296 | 1 | 74% | -104 |
| 9:30-10:30 | Jig 3 | 300 | 262 | 1 | 87% | -38 |
| 10:30-11:30 | - | 400 | - | - | - | - |
| 11:30-12:30 | - | 400 | - | - | - | - |
| 12:30-1:30 | - | 200 | - | - | - | - |
| 1:30-2:30 | - | 300 | - | - | - | - |
| 2:30-3:30 | - | 400 | - | - | - | - |
| 3:30-4:00 | - | 400 | - | - | - | - |
| Total | 1,500 | 1,328 | 6 | 89% | -172 |
CMMS: maintenance management system
A plant that runs near-24/7 needs breakdowns reported fast, work assigned and tracked, and preventive maintenance and spare parts kept on schedule, without relying on phone calls and memory.
A web-based CMMS I built for the whole plant. Production staff report problems on a public form with a priority guide (no login). The maintenance manager is alerted instantly, a technician claims the job, and the requester gets an email when it is done. PM schedules, spare parts inventory and a team performance report sit in the same system, and a daily operations report is emailed to management automatically.
One place to see open work orders, overdue PMs, equipment that is down and parts that are out of stock, for the manager and the whole maintenance team.
High production is stopped or unsafe, use for all safety issues. Medium production is partly affected and can continue at reduced capacity. Low minor issue, can wait for scheduled maintenance.
Overdue PMs (4)
| Equipment | Subject | Assigned | Overdue |
|---|---|---|---|
| Wall line conveyor | Monthly lubrication | Tech B | 9d |
| Saw 2 | Weekly guard check | Tech A | 6d |
| Dust collector | Filter inspection | Tech C | 4d |
| Air compressor | Quarterly service | Tech A | 2d |
Team activity right now
Open work orders (24)
| Equipment | Subject | Priority | Assigned | Age |
|---|---|---|---|---|
| Floor line jig 2 | Safety guard sensor fault | High | Tech A | 1d |
| Saw 1 | Not feeding to length | Medium | Tech B | 3d |
| Roller table | Roller motor noisy | Medium | Unassigned | 5d |
| Bridge saw | Dust pickup weak | High | Tech C | 2d |
| Nailer, station 7 | Misfires intermittently | Low | Unassigned | 6d |
Confirmation
You get an email with your work order number.
Alert
The maintenance manager is notified instantly.
Fix
A technician claims the job and fixes it.
Done
You get a completion email.
Sample data. Selected screens only. Not shown: user management, the equipment register, PM scheduling, full work order management, inventory and many more reports and features.
See all sample screens
Create work order
Report a problem in under a minute
Production staff use the form to report anything broken or not working right. No login needed. Maintenance takes it from there.
What happens after you submit
Priority guide
Team activity right now
Overdue PMs (4)
| Equipment | Subject | Assigned | Overdue |
|---|---|---|---|
| Wall line conveyor | Monthly lubrication | Tech B | 9d |
| Saw 2 | Weekly guard check | Tech A | 6d |
| Dust collector | Filter inspection | Tech C | 4d |
| Air compressor | Quarterly service | Tech A | 2d |
Open work orders (24)
| Equipment | Subject | Priority | Assigned | Age |
|---|---|---|---|---|
| Floor line jig 2 | Safety guard sensor fault | High | Tech A | 1d |
| Saw 1 | Not feeding to length | Medium | Tech B | 3d |
| Roller table | Roller motor noisy | Medium | Unassigned | 5d |
| Bridge saw | Dust pickup weak | High | Tech C | 2d |
| Nailer, station 7 | Misfires intermittently | Low | Unassigned | 6d |
Out of stock (3)
| # | Part ID | Part name | Location | Current | Min | Order | Unit cost | Total | Status | Action |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | CNT-2210 | Contactor, 24V coil | 1-B | 0 | 2 | +2 | $48.00 | $96.00 | Out of stock | Update stock |
| 2 | SOL-0815 | Solenoid valve, 5/2 | 4-C | 0 | 2 | +2 | $62.00 | $124.00 | Out of stock | Update stock |
| 3 | FUS-10A | Fuse 10A, box of 10 | 2-D | 0 | 4 | +4 | $9.00 | $36.00 | Out of stock | Update stock |
Team performance report
Team performance, yesterday
| Technician | WOs done | Time spent | Jobs |
|---|---|---|---|
| Technician A | 5 | 9h 10m | 5 |
| Technician B | 4 | 8h 05m | 4 |
| Technician C | 3 | 7h 30m | 3 |
| Technician D | 2 | 6h 35m | 2 |
New work orders: 3 submitted yesterday
| WO# | Subject | Type | Priority | Assigned to |
|---|---|---|---|---|
| WO-1482 | Air leak at jig 2 | Repair | High | Technician A |
| WO-1483 | Saw 1 blade change | Repair | Medium | Technician B |
| WO-1484 | Roller motor noise | Repair | Medium | Unassigned |
Currently open work orders
Open manager dashboard
Note: these are a few selected screens, shown with sample data. The real system is much larger. Not shown here: user management, the equipment register, PM scheduling, full work order management, inventory and many more reports and features.
RFI (request for information) system
Homes in production generate a steady flow of questions and issues from outside parties and internal departments. Each one has to reach the right person, be answered and closed, and its root cause and cost have to be visible.
A web system with a public submission form (site code, lot or unit, model, issue type, up to four attachments, captcha). Each RFI gets a reference number, is assigned to the responsible person, and notifies them and management by email. Internal and external RFIs move through pending, assigned, closed and archived, with departments, users, preset site codes and a full log history. Reports break RFIs down by issue type, site code, model, root-cause assessment, designer and responsible person, with cost analysis by department and by phase.
More than 4,000 RFIs have been closed through it. The reports show where issues come from and what they cost, so design, production and shipping can act on the pattern.
Reports
Assessment: root cause of RFIs
Server-side captcha and CSRF protection on the form. Up to four attachments per request. Not shown: user and department management, preset site codes, settings, the archive, the log history, external RFIs and many more reports and features.
Reference number
You get a confirmation email with a unique reference number to track the request.
Assignment
The RFI is assigned to the responsible person automatically.
Notification
The assignee and management are notified by email.
Tracking
Anyone can look up the status with the reference number.
See all sample screens
Server-side captcha and CSRF protection on the form. Up to four attachments per request.
Note: these are a few selected screens, shown with sample data. The real system is much larger. Not shown here: user and department management, preset site codes, settings, the archive, the log history, external RFIs and many more reports and features.
Shipping system: bill of lading and proof of delivery
The ERP and the scheduling system left a gap on the shipping side. There was no proper way to document what left the plant on each job, when it left, and what was still owed.
A shipping system that generates the Bill of Lading for any job. Each load is built stack by stack with weights, and loose items and hangers are marked as shipped as per the picklist or sent to back order with a note. It tracks which components shipped and when, and what is still on back order. Several photos of every load are attached as proof of shipping. Trailers, window racks and lifting straps are tracked, and a proof of delivery is generated and emailed automatically to the consignee as an electronic copy.
Shipping is documented from the bill of lading to the signed proof of delivery, with back orders and returnable equipment under control and a set of electronic reports that makes day-to-day questions quick to answer.
Bill of lading: a load built stack by stack
Generated electronically and emailed to the consignee automatically.
Sample data. The real system is much larger: company, site and phase, lot and block, transportation company and driver management, bill history, P.O. bills, trailer on delivery and trailer reports, the lifting strap count and returns, the window rack list and many more reports and features.
See all sample screens
| Sr. No. | Consignee name | Consignee email | Company | Site | Edit |
|---|---|---|---|---|---|
| 1 | Contact A | Sample Builder Inc. | SITE-A | ✎ | |
| 2 | Contact B | b@example.com | Example Developments | SITE-B | ✎ |
| 3 | Contact C | Sample Homes Group | SITE-C | ✎ | |
| 4 | Contact D | Sample Builder Inc. | SITE-D | ✎ | |
| 5 | Contact E | e@example.com | Example Developments | SITE-E | ✎ |
| 6 | Contact F | Sample Builder Inc. | SITE-A | ✎ | |
| 7 | Contact G | Sample Homes Group | SITE-F | ✎ | |
| 8 | Contact H | Sample Homes Group | SITE-F | ✎ | |
| 9 | Contact J | j@example.com | Example Developments | SITE-G | ✎ |
| 10 | Contact K | Sample Retail Group | SITE-H | ✎ |
Note: these are two selected screens, shown with sample data. The real system is much larger. Not shown here: company, site and phase, lot and block, transportation company and driver management, bill history, P.O. bills, trailer on delivery and trailer reports, the back order report, lifting strap count and returns, the window rack list, proof of delivery and many more reports and features.
The production lines I maintain
These are the automated production lines my team and I maintain, Floor Line 1 and Wall Line 1.
My work is keeping them running: mechanical and electrical troubleshooting, diagnosing PLC, HMI and SCADA faults by reading the ladder logic and SCADA tags, working with the equipment manufacturer on repairs and upgrades, and preventive maintenance with downtime tracking.
The in-house web systems above are separate tools that support this work. I troubleshoot and support the line controls (PLC and SCADA); I did not program them.
FL1 · Floor Line 1
Automated panel handling, and the safety-guarded conveyor and transfer area at station 4.
WL1 · Station 5
Framing station: a wall panel frame moving through the automated line.
Technical and leadership
Controls and automation
Systems and development
Leadership and process
Get in touch
Open to Maintenance Manager, Maintenance & Infrastructure Manager, and Automation / Controls Supervisor roles across the Greater Toronto Area.
Toronto / GTA, ON · B.Sc. Computer Science